The in-service date of the Kemper energy facility was pushed back to January and Mississippi Power said Friday the cost of the delay could be an additional $25 million to $35 million.
The in-service date of the Kemper energy facility was pushed back to January and Mississippi Power said Friday the cost of the delay could be an additional $25 million to $35 million. Photo courtesy of Mississippi Po Courtesy of Mississippi Power
The in-service date of the Kemper energy facility was pushed back to January and Mississippi Power said Friday the cost of the delay could be an additional $25 million to $35 million. Photo courtesy of Mississippi Po Courtesy of Mississippi Power

Business

Mississippi Power adds more time, more money to Kemper

December 02, 2016 4:32 PM

  Comments  

Videos