The in-service date of the Kemper energy facility was pushed back to January and Mississippi Power said Friday the cost of the delay could be an additional $25 million to $35 million.
The in-service date of the Kemper energy facility was pushed back to January and Mississippi Power said Friday the cost of the delay could be an additional $25 million to $35 million. Photo courtesy of Mississippi Po Courtesy of Mississippi Power
The in-service date of the Kemper energy facility was pushed back to January and Mississippi Power said Friday the cost of the delay could be an additional $25 million to $35 million. Photo courtesy of Mississippi Po Courtesy of Mississippi Power

Mississippi Power adds more time, more money to Kemper

December 02, 2016 04:32 PM

UPDATED December 02, 2016 04:49 PM

More Videos

  • Mayor Billy Hewes says economic projects are coming to Gulfport

    Progress is being made at the Markham, Centennial Plaza and the harbor casino, the mayor says, but he doesn't know when work will begin.